Delivery of components commences for the centre-piece of the future FAIR facility in Darmstadt, the 1,100-meter-long ring accelerator. The components are being developed and produced all over the world. The first component to be delivered was a bunch compressor, which was manufactured by Aurion Anlagentechnik GmbH in Seligenstadt, Germany, on the basis of advanced developments by GSI. GSI will first subject the bunch compressor to extensive acceptance tests. The other eight bunch compressors can be series produced once testing is completed. The bunch compressors will bundle accelerated particles into bunches that will be denser than ever before. Scientists will need such dense bunches for a large number of new experiments to be conducted at FAIR.

“FAIR’s ring accelerator will be composed of many different components that we design, develop, and plan in detail with the help of complex calculations and design studies,” says GSI project area manager Peter Spiller, who is responsible, among other things, for the construction of the ring accelerator at FAIR. “The fact that the delivery of the components has now begun is a real milestone for us. We expect to receive several additional components this year.”

“We are delighted that the development and production of the bunch compressors has enabled our small Hessian company to make a major contribution to FAIR, a globally significant high-tech project,” says Joachim Scherer, Managing Director of Aurion Anlagentechnik GmbH in Seligenstadt.

FAIR’s ring accelerator will be able to accelerate ions  from any element as well as antiprotons to almost the speed of light. Before particles are accelerated, they first have to be packed into bunches that consist of up to 500 billion ions each. The particles are then channelled to the various experiments. The size of the ion bunches depends on the experiment they are used for. The bunch compressor can generate especially short pulses that are needed for experiments in plasma physics and nuclear astrophysics, for example.

“The bunches have a temporal length of 200 to 300 nanoseconds during acceleration. This is too long for some experiments, which require the large number of ions in a shorter period of time,” says Spiller. “The bunch compressor system shortens the ion bunches to a duration of 30 to 90 nanoseconds. To do this, we use high-frequency electric fields that compress the ion pulse by rotating it in the phase space.”

“The bunch compressor is 2 metres long and 1.20 metres wide. It is 2.10 metres tall and weighs around two tons. The key structural elements are two sets of eight disks composed of special magnetic alloys that are arranged around the beamline. These disks can generate a high-frequency voltage of 40,000 Volt,” says high-frequency physicist Hans Günter König from GSI’s Ring RF department. König and his colleague Peter Hülsmann were the main people in charge of implementing the project technology and liaising with the manufacturer. “In the next step, the device will be subjected to extensive testing that will be conducted on the test rig for high-frequency systems at GSI. These tests are scheduled to be completed this spring. Series production will begin as soon as the bunch compressor has passed all of the tests.”

FAIR will be one of the largest and most complex accelerator facilities in the world. The existing GSI accelerator facility will be part of FAIR and serve as first acceleration stage. FAIR engineers and scientists will expedite technological developments in many areas in international cooperation, for example in computer science or in superconductivity techniques. Approximately 3,000 scientists from all over the world will conduct cutting-edge research at FAIR. In unique experiments they will gain new basic insights into the structure of matter and the evolution of the universe.

This press release with photos is available on our website at:
https://www.gsi.de/en/start/news/detailseite/2016/03/08/first-component-delivered-for-fairs-ring-accelerator.htm




Read previous post:
Jörg Blaurock appointed new Technical Managing Director of FAIR and GSI

As of 1 February 2016, Jörg Blaurock became the first joint Technical Managing Director of the GSI Helmholtzzentrum für Schwerionenforschung GmbH (GSI Helmholtz Centre for Heavy Ion Research) and the Facility for Antiproton and Ion Research in Europe GmbH (FAIR GmbH) in Darmstadt. Prior to this he had been working in international large-scale plant construction for over 20 years, overseeing full planning, delivery, assembly and commissioning of large technical facilities worldwide. He is now moving from General Electric in Stuttgart to Darmstadt.

Close
chemist